New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 91-100

EnsurepassQUESTION 91 You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 81-90

EnsurepassQUESTION 81 You are using Project Standard 2013. You want the ability to see only tasks that have finish dates past their deadline date. You need to achieve this goal using a custom field. What should you do?   Create…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 71-80

EnsurepassQUESTION 71 Drag Drop You are a project manager who uses Microsoft Project 2013. A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 61-70

EnsurepassQUESTION 61 You are a project manager who uses Project Professional 2013. Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 51-60

EnsurepassQUESTION 51 You are a project manager who uses Project Professional 2013. You manage a project, which involves three other colleagues who also have experience in Project Professional 2013. You and your colleagues are over budget and cannot spend any…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 41-50

EnsurepassQUESTION 41 You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks and link them in a Finish to Start…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 31-40

EnsurepassQUESTION 31 While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 21-30

EnsurepassQUESTION 21 You are a project manager for an organization that uses Project Standard 2013. You add shortcuts on the Quick Access Toolbar to your most frequently used commands. Your manager is impressed with the ease of use this customization…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 11-20

EnsurepassQUESTION 11 You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly…
Read more

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 1-10

EnsurepassQUESTION 1 You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your customer-required dates. What should you add to the project milestones?  …
Read more