Question No: 201 – (Topic 3)

Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?

  1. Start-to-Finish

  2. Finish-to-Start

  3. Start-to-Start

  4. Finish-to-Finish

Answer: B

Question No: 202 – (Topic 3)

Which of the following may require a modification to the project scope baseline?

  1. An approved project change request

  2. A team member removed from the project

  3. A task that is falling behind schedule

  4. An identified product quality issue

Answer: A

Question No: 203 – (Topic 3)

In order to meet governmental requirement Q555, all materials must meet spec #A-223 qualifications. This is an example of which of the following types of dependencies? (Select Two).

  1. Internal

  2. Discretionary

  3. Fixed

  4. External

  5. Mandatory

Answer: D,E

Question No: 204 – (Topic 3)

Which of the following is MOST likely to be included in a communication plan?

  1. Change request

  2. Risk register

  3. Frequency

  4. Statement of Work (SOW)

Answer: C

Question No: 205 – (Topic 3)

A project team is estimating the amount of time needed to perform an activity. They have

recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?

  1. PERT

  2. GANTT

  3. GERT

  4. WBS

Answer: A

Question No: 206 – (Topic 3)

Which of the following is a component of a project charter?

  1. Responsibility assignment matrix

  2. Risk register

  3. Work Breakdown Structure (WBS)

  4. Problem statement

Answer: D

Question No: 207 – (Topic 3)

Which of the following would MOST likely be reviewed during a project kick-off meeting?

  1. Change requests

  2. Work Breakdown Structure (WBS)

  3. Risk register

  4. Responsibility assignment matrix

Answer: D

Question No: 208 – (Topic 3)

Which of the following tools is the BEST to measure data organized in time sequence?

  1. Run chart

  2. Ishikawa diagram

  3. Pareto chart

  4. Histogram

Answer: A

Question No: 209 – (Topic 3)

Which of the following tools is the BEST to determine the cause of a problem?

  1. Run chart

  2. Pareto chart

  3. Ishikawa diagram

  4. Histogram

Answer: C

Question No: 210 – (Topic 3)

Which of the following documents would MOST likely be updated to reflect an approved time change for a regularly scheduled weekly status meeting?

  1. Work Breakdown Structure (WBS)

  2. Responsibility assignment matrix

  3. Communication plan

  4. Change request

Answer: C

100% Dumps4cert Free Download!
JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
JK0-017 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No