[Free] 2018(Aug) Dumps4cert CompTIA JK0-017 Dumps with VCE and PDF Download 1-10

Dumps4cert.com : Latest Dumps with PDF and VCE Files
2018 Aug CompTIA Official New Released JK0-017
100% Free Download! 100% Pass Guaranteed!

CompTIA E2C Project Certification Exam

Question No: 1 – (Topic 1)

Which of the following are process groups in the project life cycle? (Select Three).

  1. Accepting

  2. Mitigating

  3. Avoiding

  4. Initiating

  5. Closing

  6. Planning

Answer: D,E,F

Question No: 2 – (Topic 1)

A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?

  1. Storming

  2. Performing

  3. Conforming

  4. Forming

Answer: B

Question No: 3 – (Topic 1)

A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?

  1. Work Breakdown Structure (WBS)

  2. Cost management plan

  3. Approved project charter

  4. Project scope document

Answer: B

Question No: 4 – (Topic 1)

The project charter is an output of which of the following project phases?

  1. Initiation

  2. Planning

  3. Execution

  4. Closing

Answer: A

Question No: 5 – (Topic 1)

All of the following are considered part of the risk management plan EXCEPT the risk:

  1. register.

  2. matrix.

  3. assessment.

  4. baseline.

Answer: D

Question No: 6 – (Topic 1)

Which of the following is true of fast tracking a schedule?

  1. Project schedule critical path will change.

  2. Project activities will be performed concurrently.

  3. Project schedule is shortened by decreasing the project scope.

  4. Project schedule lead times are increased.

Answer: B

Question No: 7 – (Topic 1)

A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?

  1. Key Performance Indicators (KPIs)

  2. Project charter

  3. Work Breakdown Structure (WBS)

  4. Statement of Work (SOW)

Answer: C

Question No: 8 – (Topic 1)

Which of the following is the BEST communication option for team building?

  1. Send an email transmission to introduce the project.

  2. Send a completed project charter to introduce the project.

  3. Leave a voicemail message to introduce the project.

  4. Schedule a face-to-face meeting to introduce the project.

Answer: D

Question No: 9 – (Topic 1)

Which of the following is created using the work breakdown structure (WBS) as an input?

  1. Procurement management plan

  2. Vendor selection criteria

  3. Project scope statement

  4. Project charter

Answer: A

Question No: 10 – (Topic 1)

A cause and effect diagram can also be called:

  1. a control chart.

  2. a scatter diagram.

  3. an Ishikawa diagram.

  4. a Pareto Chart.

Answer: C

100% Dumps4cert Free Download!
JK0-017 PDF
100% Dumps4cert Pass Guaranteed!
JK0-017 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No